Repository LOGO
    • Login
    View Item 
    •   Intellectual Repository at Rajamangala University of Technology Phra Nakhon
    • Faculty and Institute (คณะและสถาบัน)
    • Faculty of Engineering
    • Research Report
    • View Item
    •   Intellectual Repository at Rajamangala University of Technology Phra Nakhon
    • Faculty and Institute (คณะและสถาบัน)
    • Faculty of Engineering
    • Research Report
    • View Item
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Browse

    All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

    My Account

    Login

    The effect of safety system in construction which result on productivity rate

    Thumbnail
    View/Open
    ENG_56_06.pdf (2.566Mb)
    Date
    2014-12-11
    Author
    Monkaew, Sunun
    Nawalerspunya, Thawatchai
    Teamthong, Wannawit
    Metadata
    Show full item record
    Abstract
    The purpose of this research is to study the effect of a safety system provided for external wall plastering activity on productivity by studying a construction of commercial buildings. The safety system composed of (1) stable scaffolding system, (2) providing clean and not slip walkways on the scaffold, (3) installation of handrails not less than 0.90 meters in height along sides of the scaffold, (4) installing safety nets around outside perimeters of the scaffolding, (5) indicating working area, (6) installing stairs, (7) providing protection for people who works below, (8) providing tools and equipments for transporting material which are safe and ready for using, and (9) providing personal protective equipment for workers. Cost of the safety system is 79,665 baht for a wall area of 1,510 m2, or approximately 53 baht/m2. The prevention cost is quite high because it is an initial investment cost. However, contractors could repeat theirs used on future projects. Productivity rates for prior and after the used of safety system are 1.16 and 1.13 m2/person/hr, respectively. The productivity declines for approximately 3%. In addition, our study found an impact of predecessor activity, which is a brick laying activity. If brick walls are not well aligned and plumbed, the working time for wall plastering could take longer for 8%. Meanwhile, the wall plastering productivity could decrease for 11% and labor cost could increase for 12%.
    URI
    http://repository.rmutp.ac.th/handle/123456789/1449
    Collections
    • Research Report [286]

    DSpace software copyright © 2002-2015  DuraSpace
    Contact Us | Send Feedback
    Theme by 
    @mire NV
     

     


    DSpace software copyright © 2002-2015  DuraSpace
    Contact Us | Send Feedback
    Theme by 
    @mire NV